Three workers can do a job in 28 hours. How many more workers are needed to do this job in 12 hours?

Respuesta :

MrRamon
MrRamon MrRamon
  • 13-04-2018
4 additional workers for 7 total workers.
if it takes 3 workers 28 hours to do work there are 84 total hours of work (3*28=84) to find how many workers it will take to get the work done in 12 hours divide 84 by 12. 84/12= 7 total workers. 7-3= 4 additional workers needed.
Answer Link
pranilraichura
pranilraichura pranilraichura
  • 08-03-2020

Answer:

4 workers

Step-by-step explanation:

Answer Link

Otras preguntas

can someone please help me with this i need all the answers i can get
To quickly identify a mineral sample, geologists use:
examples of dried fruits please
The song "take me out to the ball game" is an example of a song with a three-beat cycle called:
What is the lcm of 45 and 54?
If RS=59 AND ST=10x-31,find x
An enzyme that can facilitate the breakdown of amylose into smaller units is ________.
find the solution set of each pair of the following two equations algebrically
Find the cardinal number for the following sets. A​ =​ {102​, 103​, 104​, 105​,..., 155​}       B​ = ​{102​, 104​, 106​, ​..., 252​}
The storage locations within the cpu used for a particular defined purpose are called