a person can do a job in 6 day days . another can do the same job in 4days . if they work together, how long do they need to finish the job?

Respuesta :

wegnerkolmp2741o
wegnerkolmp2741o wegnerkolmp2741o
  • 01-08-2020

Answer:

It will take them 2 2/5 days working together

Step-by-step explanation:

To find the time worked

1/a + 1/b = 1/t

Where a and b are the times worked individually and t is the time worked together

1/4 + 1/6 = 1/t

Multiply each side by 12t to clear the fractions

12t( 1/4 + 1/6 = 1/t)

3t + 2t =12

Combine like terms

5t = 12

Divide by 5

t = 12/5

t = 2 2/5

It will take them 2 2/5 days working together

Answer Link

Otras preguntas

True or False- The real Plymouth rock is cracked:
Jan bought a blazer for $39.90. The price of the blazer was $38. What sales-tax rate was she charged for this blazer?
if evaporation cools the surrounding does condensation warm the surroundings ? explain
Which conquistador is not matched correctly with the region he explored or conquered?A.Hernando Cortés - western South AmericaB.Ponce de León - FloridaC.Francis
Lord of the rings: return of the King won 11 Oscar awards fact or opinion
how is the telegraph you made like the one morse made?
Which of these processes does not occur in animal cells? A. respiration B. photosynthesis C. chemical reactions D. making proteins
75% of what number is 105
Which describes the role of sunlight in chemical reactions?
In the United States today, we have a __________ system. one-party two-party multiparty four-party There are distinct separations between each level of politica